The completed Mustang CAT Long Drive facility, storefront entrance and service building under a clear sky
All results

Light industrial

Mustang CATLong Drive

An acquired facility that turned out to have no valid occupancy — brought into compliance with the City of Houston, then replaced, without the client losing a day of operation.

Location
Houston, TX

They bought a building they weren't legally allowed to occupy.

An industrial client acquired an existing facility and discovered the building did not have proper occupancy with the City of Houston. That is not a paperwork problem — it is an obstacle to operating the business at all.

They also needed a new facility on the same site, and needed to keep running while it was planned and built. Permitting was tangled further by multiple existing buildings that had been combined into a single property.

The Mustang CAT facility along its street frontage with the branded sign
The facility they acquired, on Long Drive
Aerial view of the completed facility and the equipment yard around it
One site, kept running throughout

Fix the occupancy first. Then build the new one around a working business.

We took ownership of the permitting strategy early and worked directly with the City of Houston to bring the existing facility into compliance. That cleared the immediate risk and established a path the rest of the project could be built on.

With that settled, we phased the work so the client stayed fully operational while the new facility was designed and constructed — carrying the budgeting and the decision-making support through every stage rather than handing it back at the permit desk.

An open service bay with overhead crane rail and equipment staged inside
The replacement, built around a business that never stopped

One team, start to finish

  1. Occupancy

    Took ownership of the permitting strategy and worked directly with the City of Houston to bring the existing facility into compliance.

  2. Plan

    Phased the work so the client stayed fully operational while the new facility was designed and constructed on the same site.

  3. Build

    Carried the budgeting and decision-making support straight through construction rather than handing it back at the permit desk.

  4. Handoff

    A complete facility upgrade with no downtime — the client never stopped operating.

A compliant building, a new one, and not a day lost.

A complete facility upgrade with no downtime. The client never stopped operating, and a situation that started as a legal and operational risk finished as a project that met the immediate need and the long-term one.

Aerial view of the service building with the Houston skyline on the horizon
Compliant, replaced, no downtime
Permitting solved
Solved complex permitting challenges and kept operations running — without interruption.
Compliant
Turned a non-compliant facility into a fully operational space while planning what's next.
Zero downtime
Delivered a new facility without ever shutting down the client's business.