Machine rebuilds, component repair, parts and service, and the administrative team — four operations consolidated into one purpose-built facility.

Location
Hempstead, TX
Delivery
Design-build

Four operations, one roof, and a layout that had to earn every foot.

The client wanted machine rebuilds, component repair, parts and service, and the administrative team under one roof. That only works if the layout supports heavy equipment servicing at scale and still moves people and parts cleanly between departments.

The project ran into pressure from every direction: a tight timeline, design decisions still moving, long lead times on material, and weather. Permitting got harder mid-project when the city replaced its fire marshal, pushing the review to a third party and slowing every turnaround.

Long elevation of the service building, a row of overhead doors running down the concrete apron
Heavy equipment servicing, at scale
Aerial view of the completed facility and its concrete yard, set in open farmland with the highway beyond
One roof, four operations under it

Solve it in the layout, then keep solving it in the field.

We got involved in the layout and design early, when how the building works day to day is still cheap to change. Departments were positioned around the actual flow of work, not around a generic industrial footprint.

From there it was coordination and in-house decision-making. Regular working sessions with the subcontractors, direct communication with the client, and problems caught early — a stair fabrication conflict found in the field before it became rework and a schedule hit.

A rebuild bay on the shop floor with column-mounted yellow jib cranes over a striped epoxy work zone
Rebuild bays drawn around the lift, not the footprint

One team, start to finish

  1. Plan

    Involved in layout and design early, positioning the four departments around the actual flow of work instead of a generic footprint.

  2. Permit

    Kept the review moving when the city replaced its fire marshal mid-project and everything shifted to slower third-party turnaround.

  3. Build

    Regular working sessions with the subcontractors caught field issues early — the stair fabrication conflict was solved before it became rework.

  4. Beyond

    Stayed on through the final phases and the warranty period, because the building has to keep working after the ribbon cutting.

One building doing the work of four.

A high-functioning industrial facility running large-scale operations with room for the client to grow into it. We stayed on through the final phases and the warranty period — the building keeps working after the ribbon cutting, or it wasn't finished.

View from the office mezzanine down onto the shop floor, yellow jib cranes and marked work bays below
The offices look straight down onto the work
Workflow
Optimized facility layout to improve workflow across multiple operational departments.
Four in one
Machine rebuilds, component repair, parts and service, and administration under one roof.
Through warranty
Support carried past the ribbon cutting, through final phases and the warranty period.